Overview:
The New Hope, Crystal and Golden Valley Joint Water Commission is repainting the South Water Tower located at 2801 Hillsboro Avenue. The project will include removal of the existing paint and repainting of the interior and exterior of the water tower. There will be a curtain placed around the perimeter of the tower when this working is being completed to limit debris and overspray from leaving the water tower site. A contractor will also replace multiple water valves and a hydrant at the tower site while the repainting project is underway.
Schedule:
The project will begin in April 2025 and be completed by Fall 2025, weather permitting. Work will occur Monday through Friday 7:00 AM - 8:00 PM with occasional work on Saturdays 9:00 AM - 6:00 PM.

Project Contact:
If you have any questions regarding this project please contact the city's Project Coordinator Nick Macklem at 763-592-6765 or [email protected].