2020 Crack Repair and Seal Coat Project Contract

2020 Crack Repair and Seal Coat Project Contract
Posted on 08/04/2020
At its meeting of July 27, New Hope City Council awarded the 2020 Crack Repair and Seal Coat Project contract to Allied Blacktop Company, in the amount of $74,887.40.

The city of New Hope completes annual crack repair, seal coat and fog seal application projects to extend the useful life of streets throughout the city. The streets included in the project this year were selected based upon the current pavement management plan as well as current street conditions.

Project areas include select streets northeast of Boone and 49th avenues, northwest of Boone and 42nd avenues and the New Hope Golf Course parking lot.

Work is scheduled to begin this month and completed in September. Additional information can be found by visiting newhopemn.gov/2020seal.